Kaymac Marine & Civil Engineering Ltd. was commissioned by JBA Consulting to carry out Phase 1 – Temporary Bank Protection works to a river wall within the River Great Ouse to the rear of River Terrace in St. Neots.


The works to River Terrace River Wall, St. Neots comprised the following:-

  • Mobilise to site and set up waterborne plant;
  • Load spider crane onto waterborne plant;
  • Remove surface waste such as railings and paving slabs to the site compound for disposal off site;
  • Remove any overhanging railings / slabs likely to cause further collapse;
  • Load rock filled bags onto pontoon and transfer to working area;
  • Place 3 x layers of rock filled bags using waterborne plant covering from properties 4 – 10, ending approximately 1m into the boundary of property 12 to provide additional protection to property 10;
  • Upon completion of works, remove plant from watercourse;
  • Reinstate working areas and demobilise from site.

A Spider Crane was used due to the low bridge located between the slipway at our compound and the works location.

At the end of week 1 we de-mobilised the spider crane as it was on its limit and struggled with reach to place the final bag; this was due to the rock filled bags coming in at least 20% heavier than the 2T that was specified.

To complete the works we mobilized a 14T rubber tracked excavator to site. We found a location upstream of the repair works where we could mobilize the excavator onto our barge and agreed with Huntingdonshire District Council that we could use this area before proceeding. The 14T excavator was mobilized onto the barge and completed the remaining works within 2 days.

 

 


< Back